RESOLUTION REQUESTING FULL EVALUATION OF ADDITIONAL
WASTEWATER SITES BY THE WESTERN WAKE PARTNERS
WHEREAS, the presently selected Site C for the Western Wake Wastewater Facility is located in the historic district
of the New Hill community.
WHEREAS, the presently selected Site C for the Western Wake Wastewater Facility is located near the intersection
of two major highways where smart planning places commercial development
WHEREAS, the site assessment by the partnership consultant, Hazen and Sawyer, describes a site (20) on Progress
Energy land that provides for minimum impact on the New Hill community.
WHEREAS, two sites possibly preferable to Site C exist one mile and five miles SSW of Site C, and whereas these
sites were not considered in the site evaluation process.
WHEREAS, a detailed cost analysis needs to be provided for all five sites Hazen and Sawyer considered most
favorable, and for the unevaluated site one mile SSW of Site C.
WHEREAS, inadequate time was provided for public evaluation and comment before the final Site C selection was
approved.
WHEREAS, the Apex Board of Commissioners never voted to approve the selected Site C.
WHEREAS, the New Hill community will eventually become an integral part of The Town of Apex, and the
selection of the present Site C will be detrimental to the development of this community.
NOW THEREFORE BE IT RESOLVED that the Board of Commissioners of the Town of Apex expresses its
desire to continue and expand the site evaluation process for the Western Wake Wastewater Facility to ensure that
the selection of the most equitable location is made for all concerned.
Enacted this the, 2005
Introduced by Commissioner: Jensen
Seconded by Commissioner: ---------
______________________ ____
Keith H. Weatherly
Mayor
Attest:
_____________________________
Georgia A. Evangelist
Town Clerk
|